Nortel CTO Lab 3.2 Fit-up
Value:
$300,000
Project Year: 2008 |
PCS General Contractors completed this 25,000 sf, $300,000
office fit-up in just 8 weeks. Working with HOK and BLJC, PCS was
able to maintain the original design concepts with a few time saving
adjustments to materials and complete this project within the desired
time frame.
Work included demolition of the existing office set-up, new hard
wall office partitions, new flooring, painting, HVAC, electrical,
and communication.
Working above a raised complete flooring and dealing with half
height walls possessed its challenges, but the PCS on site crew
came up with ingenious anchoring solutions that will be used on
similar future projects.
The entire project was completed while existing office space around
the project operated as usual.
|